Project Start Date: Mon 7/28/03
Project Finish Date: Fri 2/13/04
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | Work: EAI - Program Management Project | 144 days? | Mon 7/28/03 | Fri 2/13/04 | 100% | |
2 | Phase: EAI PM | 140 days | Fri 8/1/03 | Fri 2/13/04 | 100% | |
3 | Activity: PM Work | 113 days | Fri 8/1/03 | Wed 1/7/04 | 100% | |
4 | Activity: PMO Support | 104 days | Mon 8/4/03 | Fri 12/26/03 | 100% | |
5 | Activity: Attend Status Meetings | 114 days | Mon 8/18/03 | Fri 1/23/04 | 100% | |
6 | Activity: PMO Support (External) | 7 days | Wed 10/8/03 | Fri 10/17/03 | 100% | |
7 | Activity: Attend Status Meetings | 103 days | Tue 8/5/03 | Fri 12/26/03 | 100% | |
8 | Activity: Review Issues/Risks | 125 days | Fri 8/22/03 | Fri 2/13/04 | 100% | |
9 | Activity: Monitor/Review Issues/Risks | 109 days | Mon 8/11/03 | Fri 1/9/04 | 100% | |
10 | Phase: Initiation | 127 days | Mon 7/28/03 | Wed 1/21/04 | 100% | |
11 | Activity: Prepare EAI Support Structure | 3 days | Mon 9/29/03 | Wed 10/1/03 | 100% | |
12 | Activity: Develop EAI Program Initiation Material | 16 days | Mon 7/28/03 | Mon 8/18/03 | 100% | |
13 | Activity: EAI Program Initiation Material Review | 17 days | Mon 8/4/03 | Tue 8/26/03 | 100% | |
14 | Activity: Perform EAI LOE validation | 34 days | Tue 8/5/03 | Fri 9/19/03 | 100% | |
15 | Activity: EAI LOE validation review | 40 days | Mon 8/4/03 | Fri 9/26/03 | 100% | |
16 | Activity: Prepare Resource Summary from LOE | 31 days | Wed 8/6/03 | Wed 9/17/03 | 100% | |
17 | Activity: Review Resource Summary from LOE | 20 days | Mon 8/11/03 | Fri 9/5/03 | 100% | |
18 | Activity: Prepare Statement of Work (SOW) | 53 days | Wed 7/30/03 | Mon 10/13/03 | 100% | |
19 | Activity: Review/Approve SOW | 26 days | Thu 10/2/03 | Fri 11/7/03 | 100% | |
20 | Activity: Prepare Operational Concept Definition (OCD) | 19 days | Mon 10/13/03 | Fri 11/7/03 | 100% | |
21 | Activity: Review/Approve OCD | 19 days | Mon 10/13/03 | Fri 11/7/03 | 100% | |
22 | Activity: Prepare System Development Plan (SDP) | 55 days | Mon 7/28/03 | Mon 10/13/03 | 100% | |
23 | Activity: Review/Approve SDP | 54 days | Mon 8/18/03 | Fri 10/31/03 | 100% | |
24 | Activity: Prepare BR / SR Matrix | 23 days | Mon 10/13/03 | Thu 11/13/03 | 100% | |
25 | Activity: Review/Approve BR / SR Matrix | 19 days | Mon 10/13/03 | Fri 11/7/03 | 100% | |
26 | Activity: Prepare Resource Requirements Plan | 56 days | Tue 7/29/03 | Wed 10/15/03 | 100% | |
27 | Activity: Review/Approve Resource Requirements Plan | 115 days | Wed 8/13/03 | Wed 1/21/04 | 100% | |
28 | Activity: Prepare Roles and Responsibilities | 113 days | Fri 8/8/03 | Wed 1/14/04 | 100% | |
29 | Activity: Review/Approve Roles and Responsibilities | 42 days | Wed 8/20/03 | Fri 10/17/03 | 100% | |
30 | Phase: EAI Start Planning | 56 days? | Thu 10/2/03 | Fri 12/19/03 | 100% | |
31 | Activity: Prepare EAI Support Structure | 2 days? | Thu 10/9/03 | Mon 10/13/03 | 100% | |
32 | Activity: Establish Process Project Phase 1 | 6 days? | Thu 10/2/03 | Thu 10/9/03 | 100% | |
33 | Activity: Establish Process Project Risk Plan | 6 days? | Thu 10/9/03 | Fri 10/17/03 | 100% | |
34 | Activity: Establish Framework Project Phase 1 | 16 days? | Mon 10/13/03 | Tue 11/4/03 | 100% | |
35 | Activity: Attend Meetings | 50 days? | Fri 10/10/03 | Fri 12/19/03 | 100% | |
36 | Activity: Review Program Material | 3 days? | Mon 10/6/03 | Wed 10/8/03 | 100% | |
37 | Activity: Review EV Methodology & PMO setup | 6 days? | Thu 10/9/03 | Fri 10/17/03 | 100% | |
38 | Activity: Attend meetings | 54 days? | Mon 10/6/03 | Fri 12/19/03 | 100% |
ID | Name | Group | Max Units | Peak Units |
---|---|---|---|---|
1 | Variable Resource 1 | 100% | 0% | |
2 | Variable Resource 2 | 100% | 0% | |
3 | Variable Resource 3 | 100% | 0% | |
4 | Variable Resource 4 | 100% | 0% |
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|