EAI Program


Project Start Date: Mon 7/28/03
Project Finish Date: Fri 2/13/04

Tasks

ID
Task Name
DurationStartFinishResource Names% Complete
1
Work: EAI - Program Management Project
144 days?Mon 7/28/03Fri 2/13/04 100%
2
Phase: EAI PM
140 daysFri 8/1/03Fri 2/13/04 100%
3
Activity: PM Work
113 daysFri 8/1/03Wed 1/7/04 100%
4
Activity: PMO Support
104 daysMon 8/4/03Fri 12/26/03 100%
5
Activity: Attend Status Meetings
114 daysMon 8/18/03Fri 1/23/04 100%
6
Activity: PMO Support (External)
7 daysWed 10/8/03Fri 10/17/03 100%
7
Activity: Attend Status Meetings
103 daysTue 8/5/03Fri 12/26/03 100%
8
Activity: Review Issues/Risks
125 daysFri 8/22/03Fri 2/13/04 100%
9
Activity: Monitor/Review Issues/Risks
109 daysMon 8/11/03Fri 1/9/04 100%
10
Phase: Initiation
127 daysMon 7/28/03Wed 1/21/04 100%
11
Activity: Prepare EAI Support Structure
3 daysMon 9/29/03Wed 10/1/03 100%
12
Activity: Develop EAI Program Initiation Material
16 daysMon 7/28/03Mon 8/18/03 100%
13
Activity: EAI Program Initiation Material Review
17 daysMon 8/4/03Tue 8/26/03 100%
14
Activity: Perform EAI LOE validation
34 daysTue 8/5/03Fri 9/19/03 100%
15
Activity: EAI LOE validation review
40 daysMon 8/4/03Fri 9/26/03 100%
16
Activity: Prepare Resource Summary from LOE
31 daysWed 8/6/03Wed 9/17/03 100%
17
Activity: Review Resource Summary from LOE
20 daysMon 8/11/03Fri 9/5/03 100%
18
Activity: Prepare Statement of Work (SOW)
53 daysWed 7/30/03Mon 10/13/03 100%
19
Activity: Review/Approve SOW
26 daysThu 10/2/03Fri 11/7/03 100%
20
Activity: Prepare Operational Concept Definition (OCD)
19 daysMon 10/13/03Fri 11/7/03 100%
21
Activity: Review/Approve OCD
19 daysMon 10/13/03Fri 11/7/03 100%
22
Activity: Prepare System Development Plan (SDP)
55 daysMon 7/28/03Mon 10/13/03 100%
23
Activity: Review/Approve SDP
54 daysMon 8/18/03Fri 10/31/03 100%
24
Activity: Prepare BR / SR Matrix
23 daysMon 10/13/03Thu 11/13/03 100%
25
Activity: Review/Approve BR / SR Matrix
19 daysMon 10/13/03Fri 11/7/03 100%
26
Activity: Prepare Resource Requirements Plan
56 daysTue 7/29/03Wed 10/15/03 100%
27
Activity: Review/Approve Resource Requirements Plan
115 daysWed 8/13/03Wed 1/21/04 100%
28
Activity: Prepare Roles and Responsibilities
113 daysFri 8/8/03Wed 1/14/04 100%
29
Activity: Review/Approve Roles and Responsibilities
42 daysWed 8/20/03Fri 10/17/03 100%
30
Phase: EAI Start Planning
56 days?Thu 10/2/03Fri 12/19/03 100%
31
Activity: Prepare EAI Support Structure
2 days?Thu 10/9/03Mon 10/13/03 100%
32
Activity: Establish Process Project Phase 1
6 days?Thu 10/2/03Thu 10/9/03 100%
33
Activity: Establish Process Project Risk Plan
6 days?Thu 10/9/03Fri 10/17/03 100%
34
Activity: Establish Framework Project Phase 1
16 days?Mon 10/13/03Tue 11/4/03 100%
35
Activity: Attend Meetings
50 days?Fri 10/10/03Fri 12/19/03 100%
36
Activity: Review Program Material
3 days?Mon 10/6/03Wed 10/8/03 100%
37
Activity: Review EV Methodology & PMO setup
6 days?Thu 10/9/03Fri 10/17/03 100%
38
Activity: Attend meetings
54 days?Mon 10/6/03Fri 12/19/03 100%

Resources

IDNameGroupMax UnitsPeak Units
1Variable Resource 1 100%0%
2Variable Resource 2 100%0%
3Variable Resource 3 100%0%
4Variable Resource 4 100%0%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete