Project Start Date: Mon 2/24/03
Project Finish Date: Wed 12/24/03
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | ICBN Program | 169 days | Fri 5/2/03 | Wed 12/24/03 | 100% | |
2 | Project: Admin Interface - Phase II | 169 days | Fri 5/2/03 | Wed 12/24/03 | 100% | |
3 | Initiation | 39 days | Fri 5/2/03 | Wed 6/25/03 | 100% | |
4 | System Development | 20 days | Thu 5/29/03 | Wed 6/25/03 | 100% | |
5 | Gather non-functional requirements | 10 days | Thu 5/29/03 | Wed 6/11/03 | Project Manager - EAI[50%],PMO - EAI[50%],Subject Matter Expert - EAI | 100% |
6 | Gather functional requirements | 10 days | Thu 6/12/03 | Wed 6/25/03 | Project Manager - EAI[50%],PMO - EAI[50%],Subject Matter Expert - EAI | 100% |
7 | Project Management | 22 days | Fri 5/2/03 | Mon 6/2/03 | 100% | |
8 | Identify current client initiatives that might be related to this project | 2 days | Fri 5/2/03 | Mon 5/5/03 | Project Manager - EAI,PMO - EAI[50%],Subject Matter Expert - EAI[50%] | 100% |
9 | Define criteria for project success (I.e. critical success factors) | 4 days | Tue 5/6/03 | Fri 5/9/03 | Project Manager - EAI[50%],PMO - EAI[50%],Subject Matter Expert - EAI[25%] | 100% |
10 | Identify assumptions and risks | 4 days | Mon 5/12/03 | Thu 5/15/03 | Project Manager - EAI[25%],PMO - EAI[50%],Subject Matter Expert - EAI[25%] | 100% |
11 | Identify and establish project organization [internal & external] | 2 days | Fri 5/16/03 | Mon 5/19/03 | Project Manager - EAI[50%],PMO - EAI,Subject Matter Expert - EAI[50%] | 100% |
12 | Establish and implement change control process | 4 days | Tue 5/20/03 | Fri 5/23/03 | Subject Matter Expert - EAI[25%],PMO - EAI[50%],Project Manager - EAI[50%] | 100% |
13 | Document project charter and communicate to stake holders | 2 days | Mon 5/26/03 | Tue 5/27/03 | Project Manager - EAI,PMO - EAI[50%] | 100% |
14 | Develop Work Plan and Communicate | 4 days | Wed 5/28/03 | Mon 6/2/03 | Project Manager - EAI[50%],PMO - EAI[25%] | 100% |
15 | Complete Project Charter and SDP | 0 days | Mon 6/2/03 | Mon 6/2/03 | 100% | |
16 | Planning | 15 days | Thu 6/26/03 | Wed 7/16/03 | 100% | |
17 | System Development | 15 days | Thu 6/26/03 | Wed 7/16/03 | 100% | |
18 | Define Business Requirements | 3 days | Thu 6/26/03 | Mon 6/30/03 | Project Manager - EAI[167%],Quality Assurance/Testing - EAI[167%],Subject Matter Expert - EAI[167%] | 100% |
19 | Define Operations Concept | 3 days | Tue 7/1/03 | Thu 7/3/03 | System Architect - EAI[167%],Subject Matter Expert - EAI[167%],Quality Assurance/Testing - EAI[167%] | 100% |
20 | Perform Stakeholder Analysis | 3 days | Fri 7/4/03 | Tue 7/8/03 | Project Manager - EAI[33%],Quality Assurance/Testing - EAI[200%],Subject Matter Expert - EAI[200%],System Architect - EAI[166%] | 100% |
21 | Construct/Deliver Communication Materials | 3 days | Wed 7/9/03 | Fri 7/11/03 | PMO - EAI[200%],Subject Matter Expert - EAI[200%],System Architect - EAI[200%] | 100% |
22 | Conduct Startup Technical Review | 3 days | Mon 7/14/03 | Wed 7/16/03 | Subject Matter Expert - EAI[200%] | 100% |
23 | Project Management | 4 days | Thu 6/26/03 | Tue 7/1/03 | 100% | |
24 | Document Assumption and Risk Mitigations | 1 day | Thu 6/26/03 | Thu 6/26/03 | PMO - EAI[500%] | 100% |
25 | Identify Framework Setup Team | 1 day | Fri 6/27/03 | Fri 6/27/03 | Project Manager - EAI[200%],PMO - EAI,Subject Matter Expert - EAI | 100% |
26 | Plan Project SQA activities | 1 day | Mon 6/30/03 | Mon 6/30/03 | Project Manager - EAI[500%],PMO - EAI[200%],Quality Assurance/Testing - EAI[500%],Subject Matter Expert - EAI[200%] | 100% |
27 | Update Work plan and communicate | 1 day | Tue 7/1/03 | Tue 7/1/03 | Project Manager - EAI[200%],PMO - EAI | 100% |
28 | Planning Complete | 0 days | Tue 7/1/03 | Tue 7/1/03 | 100% | |
29 | Analysis | 12 days | Thu 7/17/03 | Fri 8/1/03 | 100% | |
30 | System Development | 12 days | Thu 7/17/03 | Fri 8/1/03 | 100% | |
31 | Define System Requirements | 2 days | Thu 7/17/03 | Fri 7/18/03 | Quality Assurance/Testing - EAI,Subject Matter Expert - EAI[250%],System Architect - EAI[150%] | 100% |
32 | Analyze And Allocate System Requirements | 1 day | Mon 7/21/03 | Mon 7/21/03 | System Architect - EAI[500%] | 100% |
33 | Revisit & Update Infrastructure Conceptual Design | 2 days | Tue 7/22/03 | Wed 7/23/03 | Subject Matter Expert - EAI[250%] | 100% |
34 | Evaluate Recommended Solutions | 2 days | Thu 7/24/03 | Fri 7/25/03 | Quality Assurance/Testing - EAI,Subject Matter Expert - EAI[200%],System Architect - EAI[200%] | 100% |
35 | Define User Acceptance Criteria | 1 day | Mon 7/28/03 | Mon 7/28/03 | PMO - EAI[300%],Subject Matter Expert - EAI[500%],System Architect - EAI[200%] | 100% |
36 | Perform Requirements Technical Reviews | 2 days | Tue 7/29/03 | Wed 7/30/03 | PMO - EAI[50%] | 100% |
37 | Construct/Deliver Communication Materials | 2 days | Thu 7/31/03 | Fri 8/1/03 | Subject Matter Expert - EAI[250%] | 100% |
38 | Project Management | 5 days | Thu 7/17/03 | Wed 7/23/03 | 100% | |
39 | Document Assumption and Risk Mitigations | 1 day | Thu 7/17/03 | Thu 7/17/03 | PMO - EAI[200%],Project Manager - EAI[200%],System Architect - EAI[300%] | 100% |
40 | Review change control process | 1 day | Fri 7/18/03 | Fri 7/18/03 | Project Manager - EAI[200%],PMO - EAI[300%],System Architect - EAI[200%] | 100% |
41 | Identify critical tasks / activities | 1 day | Mon 7/21/03 | Mon 7/21/03 | Project Manager - EAI[500%],PMO - EAI[200%] | 100% |
42 | Update Work plan and communicate | 2 days | Tue 7/22/03 | Wed 7/23/03 | Project Manager - EAI[150%],PMO - EAI[50%] | 100% |
43 | Preliminary Design | 21 days | Mon 8/4/03 | Mon 9/1/03 | 100% | |
44 | System Development | 21 days | Mon 8/4/03 | Mon 9/1/03 | 100% | |
45 | Finalize User Acceptance Criteria | 5 days | Mon 8/4/03 | Fri 8/8/03 | Project Manager - EAI,Quality Assurance/Testing - EAI[20%],Subject Matter Expert - EAI[40%],System Architect - EAI[80%] | 100% |
46 | Develop Component Interface Chart | 5 days | Mon 8/4/03 | Fri 8/8/03 | Infrastructure Support - EAI,Quality Assurance/Testing - EAI[20%],Subject Matter Expert - EAI[40%],System Architect - EAI[80%] | 100% |
47 | Define To-be Physical Architecture | 4 days | Mon 8/11/03 | Thu 8/14/03 | 100% | |
48 | Define S/w Configurations | 4 days | Mon 8/11/03 | Thu 8/14/03 | Infrastructure Support - EAI[50%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[50%] | 100% |
49 | Assess System Impact | 4 days | Mon 8/4/03 | Thu 8/7/03 | Project Manager - EAI[125%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI | 100% |
50 | Perform Preliminary Architecture Design | 6 days | Fri 8/15/03 | Fri 8/22/03 | 100% | |
51 | Perform Functional Requirement Assessment | 3 days | Fri 8/15/03 | Tue 8/19/03 | Project Manager - EAI[101%],Infrastructure Support - EAI[167%],Quality Assurance/Testing - EAI[33%],Subject Matter Expert - EAI[66%],System Architect - EAI[133%] | 100% |
52 | Perform Non-Functional Requirement Assessment | 3 days | Wed 8/20/03 | Fri 8/22/03 | PMO - EAI[66%],Infrastructure Support - EAI[167%],Quality Assurance/Testing - EAI[33%],Subject Matter Expert - EAI[66%],System Architect - EAI[134%] | 100% |
53 | Perform To-Be Solution Gap Analysis | 6 days | Mon 8/25/03 | Mon 9/1/03 | 100% | |
54 | Negotiate Requirements Changes | 6 days | Mon 8/25/03 | Mon 9/1/03 | Project Manager - EAI[16%],PMO - EAI[67%],System Architect - EAI[84%] | 100% |
55 | Construct/Deliver Communications Materials | 0 days | Mon 9/1/03 | Mon 9/1/03 | 100% | |
56 | Project Management | 3 days | Mon 8/4/03 | Wed 8/6/03 | 100% | |
57 | Document Assumption and Risk Mitigations | 1 day | Mon 8/4/03 | Mon 8/4/03 | Project Manager - EAI[500%],PMO - EAI[200%] | 100% |
58 | Identify critical tasks / activities | 1 day | Tue 8/5/03 | Tue 8/5/03 | Project Manager - EAI[500%],PMO - EAI[200%] | 100% |
59 | Update Work plan and communicate | 1 day | Wed 8/6/03 | Wed 8/6/03 | Project Manager - EAI[300%],PMO - EAI | 100% |
60 | Detailed Design | 21 days | Mon 9/1/03 | Tue 9/30/03 | 100% | |
61 | System Development | 0 days | Mon 9/1/03 | Mon 9/1/03 | 100% | |
62 | Perform Detailed Architecture Design | 0 days | Mon 9/1/03 | Mon 9/1/03 | 100% | |
63 | Finalize To Be Logical Architecture | 0 days | Mon 9/1/03 | Mon 9/1/03 | 100% | |
64 | Finalize S/W configurations | 0 days | Mon 9/1/03 | Mon 9/1/03 | 100% | |
65 | Develop Test Plans And Specifications | 12 days | Tue 9/2/03 | Wed 9/17/03 | 100% | |
66 | S/W Components, Integration And System | 3 days | Tue 9/2/03 | Thu 9/4/03 | Database Administrator - EAI,Infrastructure Support - EAI[166%],Subject Matter Expert - EAI[334%] | 100% |
67 | Operational Dry Run | 3 days | Fri 9/5/03 | Tue 9/9/03 | Database Administrator - EAI[66%],Infrastructure Support - EAI[66%],Subject Matter Expert - EAI[134%] | 100% |
68 | Develop Business Continuity Plan | 3 days | Wed 9/10/03 | Fri 9/12/03 | PMO - EAI[67%],Subject Matter Expert - EAI[33%] | 100% |
69 | Develop implementation plan | 3 days | Mon 9/15/03 | Wed 9/17/03 | PMO - EAI[67%],Subject Matter Expert - EAI[33%] | 100% |
70 | Develop Construction Specifications | 21 days | Tue 9/2/03 | Tue 9/30/03 | 100% | |
71 | Evaluate Existing component Re-Use | 3 days | Thu 9/18/03 | Mon 9/22/03 | Subject Matter Expert - EAI[333%] | 100% |
72 | Perform Detailed Design Technical Review | 3 days | Tue 9/23/03 | Thu 9/25/03 | Project Manager - EAI[167%] | 100% |
73 | Construct / Deliver Communication Materials | 3 days | Fri 9/26/03 | Tue 9/30/03 | PMO - EAI[67%] | 100% |
74 | Monitor Developer Communications | 2 days | Tue 9/2/03 | Wed 9/3/03 | Project Manager - EAI[200%],PMO - EAI[50%] | 100% |
75 | Project Management | 18 days | Tue 9/2/03 | Thu 9/25/03 | 100% | |
76 | Document Assumption and Risk Mitigations | 5 days | Tue 9/2/03 | Mon 9/8/03 | Project Manager - EAI,PMO - EAI[40%] | 100% |
77 | Review change control process | 5 days | Tue 9/9/03 | Mon 9/15/03 | Project Manager - EAI,PMO - EAI[40%] | 100% |
78 | Identify critical tasks / activities | 5 days | Tue 9/16/03 | Mon 9/22/03 | Project Manager - EAI,PMO - EAI[40%] | 100% |
79 | Update Work plan and communicate | 3 days | Tue 9/23/03 | Thu 9/25/03 | Project Manager - EAI,PMO - EAI[33%] | 100% |
80 | Construction And Integration | 20 days | Wed 10/1/03 | Tue 10/28/03 | 100% | |
81 | System Development | 20 days | Wed 10/1/03 | Tue 10/28/03 | 100% | |
82 | Install complementary software (e.g JDK, Network tools etc) | 5 days | Wed 10/1/03 | Tue 10/7/03 | Database Administrator - EAI[26%],Infrastructure Support - EAI[169%],Subject Matter Expert - EAI[85%] | 100% |
83 | Build / Customize Components | 5 days | Wed 10/8/03 | Tue 10/14/03 | Infrastructure Support - EAI[200%],Subject Matter Expert - EAI | 100% |
84 | Integrate System Components | 5 days | Wed 10/15/03 | Tue 10/21/03 | Infrastructure Support - EAI[200%],Subject Matter Expert - EAI | 100% |
85 | Perform Unit Testing | 5 days | Wed 10/22/03 | Tue 10/28/03 | Infrastructure Support - EAI[200%] | 100% |
86 | Update Business Continuity Plan | 1 day | Wed 10/1/03 | Wed 10/1/03 | PMO - EAI,Subject Matter Expert - EAI | 100% |
87 | Update implementation plan | 2 days | Wed 10/1/03 | Thu 10/2/03 | Subject Matter Expert - EAI[50%],PMO - EAI[50%] | 100% |
88 | Finalize System Test Plans And Specifications | 3 days | Wed 10/1/03 | Fri 10/3/03 | Subject Matter Expert - EAI | 100% |
89 | Perform Integration Testing | 5 days | Wed 10/1/03 | Tue 10/7/03 | Infrastructure Support - EAI | 100% |
90 | Develop System Documentation | 5 days | Wed 10/1/03 | Tue 10/7/03 | 100% | |
91 | System Operational Procedures | 5 days | Wed 10/1/03 | Tue 10/7/03 | Subject Matter Expert - EAI | 100% |
92 | User Manual | 5 days | Wed 10/1/03 | Tue 10/7/03 | Subject Matter Expert - EAI[200%] | 100% |
93 | Perform System Test Readiness Technical Review | 5 days | Wed 10/1/03 | Tue 10/7/03 | Project Manager - EAI | 100% |
94 | Construct / Deliver Communication Materials | 2 days | Wed 10/1/03 | Thu 10/2/03 | PMO - EAI | 100% |
95 | Monitor Vendor Communications | 5 days | Wed 10/1/03 | Tue 10/7/03 | Project Manager - EAI | 100% |
96 | Project Management | 18 days | Wed 10/1/03 | Fri 10/24/03 | 100% | |
97 | Document Assumption and Risk Mitigations | 5 days | Wed 10/1/03 | Tue 10/7/03 | Project Manager - EAI[112%],PMO - EAI[28%] | 100% |
98 | Review change control process | 5 days | Wed 10/8/03 | Tue 10/14/03 | Project Manager - EAI[112%],PMO - EAI[28%] | 100% |
99 | Identify critical tasks / activities | 5 days | Wed 10/15/03 | Tue 10/21/03 | Project Manager - EAI[112%],PMO - EAI[28%] | 100% |
100 | Update Work plan and communicate | 3 days | Wed 10/22/03 | Fri 10/24/03 | Project Manager - EAI[103%],PMO - EAI[31%] | 100% |
101 | System Test And Acceptance | 20 days | Wed 10/29/03 | Tue 11/25/03 | 100% | |
102 | System Development | 20 days | Wed 10/29/03 | Tue 11/25/03 | 100% | |
103 | Train Operational Dry Run (ODR) Participants | 2 days | Wed 10/29/03 | Thu 10/30/03 | Infrastructure Support - EAI,Quality Assurance/Testing - EAI | 100% |
104 | Perform System Test | 20 days | Wed 10/29/03 | Tue 11/25/03 | 100% | |
105 | Stress Testing | 5 days | Fri 10/31/03 | Thu 11/6/03 | Infrastructure Support - EAI[200%],Subject Matter Expert - EAI[200%] | 100% |
106 | Operational Dry Run (Business Processes) | 5 days | Fri 11/7/03 | Thu 11/13/03 | System Architect - EAI[200%],Infrastructure Support - EAI[200%] | 100% |
107 | Perform User Acceptance Test | 5 days | Fri 11/14/03 | Thu 11/20/03 | Infrastructure Support - EAI,Subject Matter Expert - EAI | 100% |
108 | Conduct Business Continuity Test | 1 day | Fri 11/21/03 | Fri 11/21/03 | Subject Matter Expert - EAI[200%] | 100% |
109 | Update System Documentation | 1 day | Wed 10/29/03 | Wed 10/29/03 | PMO - EAI | 100% |
110 | Conduct IT Certification | 1 day | Mon 11/24/03 | Mon 11/24/03 | PMO - EAI | 100% |
111 | Perform Pre-Implementation Technical Review | 1 day | Tue 11/25/03 | Tue 11/25/03 | Subject Matter Expert - EAI | 100% |
112 | Finalize Business Continuity Plan | 1 day | Mon 11/24/03 | Mon 11/24/03 | PMO - EAI[50%],Subject Matter Expert - EAI[50%] | 100% |
113 | Finalize Implementation plan | 2 days | Wed 10/29/03 | Thu 10/30/03 | PMO - EAI[50%],Subject Matter Expert - EAI[50%] | 100% |
114 | Construct / Deliver Communication Materials | 1 day | Wed 10/29/03 | Wed 10/29/03 | PMO - EAI[200%] | 100% |
115 | Monitor Vendor Communications | 5 days | Wed 10/29/03 | Tue 11/4/03 | Project Manager - EAI[60%],PMO - EAI[40%] | 100% |
116 | Project Management | 5 days | Wed 10/29/03 | Tue 11/4/03 | 100% | |
117 | Document Assumption and Risk Mitigations | 5 days | Wed 10/29/03 | Tue 11/4/03 | Project Manager - EAI[112%],PMO - EAI[28%] | 100% |
118 | Review change control process | 5 days | Wed 10/29/03 | Tue 11/4/03 | PMO - EAI[28%],Project Manager - EAI[112%] | 100% |
119 | Identify critical tasks / activities | 5 days | Wed 10/29/03 | Tue 11/4/03 | PMO - EAI[28%],Project Manager - EAI[112%] | 100% |
120 | Update Work plan and communicate | 3 days | Wed 10/29/03 | Fri 10/31/03 | Project Manager - EAI,PMO - EAI[33%] | 100% |
121 | Implementation | 15 days | Wed 11/26/03 | Tue 12/16/03 | 100% | |
122 | System Development | 15 days | Wed 11/26/03 | Tue 12/16/03 | 100% | |
123 | Execute Implementation Plan | 2 days | Wed 11/26/03 | Thu 11/27/03 | Project Manager - EAI | 100% |
124 | Commission System | 2 days | Wed 11/26/03 | Thu 11/27/03 | 100% | |
125 | Development Environment | 2 days | Wed 11/26/03 | Thu 11/27/03 | Business Analyst - EAI,Database Administrator - EAI,Infrastructure Support - EAI,Quality Assurance/Testing - EAI,Subject Matter Expert - EAI,System Architect - EAI | 100% |
126 | Test Environment | 2 days | Wed 11/26/03 | Thu 11/27/03 | System Architect - EAI,Subject Matter Expert - EAI,Quality Assurance/Testing - EAI,Infrastructure Support - EAI,Database Administrator - EAI,Business Analyst - EAI | 100% |
127 | Staging Environment | 2 days | Wed 11/26/03 | Thu 11/27/03 | Business Analyst - EAI,Database Administrator - EAI,Infrastructure Support - EAI,Quality Assurance/Testing - EAI,Subject Matter Expert - EAI,System Architect - EAI | 100% |
128 | DR Environment | 2 days | Wed 11/26/03 | Thu 11/27/03 | System Architect - EAI,Subject Matter Expert - EAI,Quality Assurance/Testing - EAI,Infrastructure Support - EAI,Database Administrator - EAI,Business Analyst - EAI | 100% |
129 | Production Environment | 2 days | Wed 11/26/03 | Thu 11/27/03 | Business Analyst - EAI[116%],Database Administrator - EAI[97%],Infrastructure Support - EAI[97%],Quality Assurance/Testing - EAI[97%],Subject Matter Expert - EAI[97%],System Architect - EAI[97%] | 100% |
130 | Train Operational Staff | 6 days | Fri 11/28/03 | Fri 12/5/03 | Infrastructure Support - EAI[167%] | 100% |
131 | Test Operational Procedures | 5 days | Mon 12/8/03 | Fri 12/12/03 | Infrastructure Support - EAI | 100% |
132 | Finalize System Documentation | 2 days | Mon 12/15/03 | Tue 12/16/03 | PMO - EAI,Infrastructure Support - EAI[50%] | 100% |
133 | Construct / Deliver Communication Materials | 2 days | Wed 11/26/03 | Thu 11/27/03 | PMO - EAI | 100% |
134 | Monitor Developer Communications | 2 days | Wed 11/26/03 | Thu 11/27/03 | PMO - EAI[50%],Project Manager - EAI | 100% |
135 | Project Management | 4 days | Wed 11/26/03 | Mon 12/1/03 | 100% | |
136 | Document Assumption and Risk Mitigations | 2 days | Wed 11/26/03 | Thu 11/27/03 | Project Manager - EAI,PMO - EAI[150%],Infrastructure Support - EAI | 100% |
137 | Review change control process | 2 days | Wed 11/26/03 | Thu 11/27/03 | Project Manager - EAI,PMO - EAI[250%] | 100% |
138 | Identify critical tasks / activities | 3 days | Wed 11/26/03 | Fri 11/28/03 | Project Manager - EAI[104%],PMO - EAI[65%],System Architect - EAI[65%] | 100% |
139 | Update Work plan and communicate | 4 days | Wed 11/26/03 | Mon 12/1/03 | Project Manager - EAI | 100% |
140 | Operations And Maintenance | 23 days | Mon 11/24/03 | Wed 12/24/03 | 100% | |
141 | System Development | 23 days | Mon 11/24/03 | Wed 12/24/03 | 100% | |
142 | Identify Support Team | 2 days | Mon 11/24/03 | Tue 11/25/03 | Project Manager - EAI[50%],PMO - EAI[50%] | 100% |
143 | Define Application Handover Plan | 3 days | Mon 11/24/03 | Wed 11/26/03 | Project Manager - EAI[33%],PMO - EAI[33%],Business Analyst - EAI[67%],Database Administrator - EAI[33%],Subject Matter Expert - EAI[67%],System Architect - EAI[33%] | 100% |
144 | Create a primary Support Plan | 4 days | Thu 11/27/03 | Tue 12/2/03 | Project Manager - EAI[25%],PMO - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
145 | Refine the support process | 4 days | Wed 12/3/03 | Mon 12/8/03 | Business Analyst - EAI[25%],Subject Matter Expert - EAI[25%],System Architect - EAI[25%] | 100% |
146 | Details of all servers | 4 days | Wed 12/3/03 | Mon 12/8/03 | Business Analyst - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[50%] | 100% |
147 | Define System Operation Procedure | 4 days | Tue 12/9/03 | Fri 12/12/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
148 | Define Build Procedure | 4 days | Tue 12/9/03 | Fri 12/12/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
149 | Define QA Procedure | 4 days | Tue 12/9/03 | Fri 12/12/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
150 | Define Release Procedure | 4 days | Mon 12/15/03 | Thu 12/18/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
151 | Define Defect Life Cycle Procedure | 4 days | Mon 12/15/03 | Thu 12/18/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
152 | Define Support level Process | 4 days | Mon 12/15/03 | Thu 12/18/03 | Business Analyst - EAI[50%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
153 | Complete handover to support team | 4 days | Fri 12/19/03 | Wed 12/24/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%],Project Manager - EAI[25%],PMO - EAI[50%] | 100% |
154 | Train support team on technology | 4 days | Fri 12/19/03 | Wed 12/24/03 | Application Developer - EAI[25%],Business Analyst - EAI[50%],Database Administrator - EAI[25%],Quality Assurance/Testing - EAI[25%],Subject Matter Expert - EAI[50%],System Architect - EAI[25%] | 100% |
155 | Project Management | 8 days | Mon 11/24/03 | Wed 12/3/03 | 100% | |
156 | Establish and implement change control process | 4 days | Mon 11/24/03 | Thu 11/27/03 | Project Manager - EAI[50%],PMO - EAI[50%],Business Analyst - EAI[75%],Quality Assurance/Testing - EAI[50%],Subject Matter Expert - EAI[75%],System Architect - EAI[50%] | 100% |
157 | Document project charter and communicate to stakeholders | 4 days | Fri 11/28/03 | Wed 12/3/03 | Project Manager - EAI[25%],PMO - EAI[25%] | 100% |
ID | Name | Group | Max Units | Peak Units |
---|---|---|---|---|
1 | Project Manager - EAI | 100% | 0% | |
2 | PMO - EAI | 100% | 0% | |
3 | Subject Matter Expert - EAI | 100% | 0% | |
4 | Quality Assurance/Testing - EAI | 100% | 0% | |
5 | System Architect - EAI | 100% | 0% | |
6 | Infrastructure Support - EAI | 100% | 0% | |
7 | Database Administrator - EAI | 100% | 0% | |
8 | Business Analyst - EAI | 100% | 0% | |
9 | Application Developer - EAI | 100% | 0% | |
10 | Functional Analyst - EAI | 100% | 0% | |
11 | OCM - EAI | 100% | 0% | |
12 | Portal Web Master - EAI | 100% | 0% |
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|---|---|---|---|---|---|
5 | Gather non-functional requirements | Project Manager - EAI | 40 hrs | Thu 5/29/03 | Wed 6/11/03 | 100% |
5 | Gather non-functional requirements | PMO - EAI | 40 hrs | Thu 5/29/03 | Wed 6/11/03 | 100% |
5 | Gather non-functional requirements | Subject Matter Expert - EAI | 80 hrs | Thu 5/29/03 | Wed 6/11/03 | 100% |
6 | Gather functional requirements | Project Manager - EAI | 40 hrs | Thu 6/12/03 | Wed 6/25/03 | 100% |
6 | Gather functional requirements | PMO - EAI | 40 hrs | Thu 6/12/03 | Wed 6/25/03 | 100% |
6 | Gather functional requirements | Subject Matter Expert - EAI | 80 hrs | Thu 6/12/03 | Wed 6/25/03 | 100% |
8 | Identify current client initiatives that might be related to this project | Project Manager - EAI | 16 hrs | Fri 5/2/03 | Mon 5/5/03 | 100% |
8 | Identify current client initiatives that might be related to this project | PMO - EAI | 8 hrs | Fri 5/2/03 | Mon 5/5/03 | 100% |
8 | Identify current client initiatives that might be related to this project | Subject Matter Expert - EAI | 8 hrs | Fri 5/2/03 | Mon 5/5/03 | 100% |
9 | Define criteria for project success (I.e. critical success factors) | Project Manager - EAI | 16 hrs | Tue 5/6/03 | Fri 5/9/03 | 100% |
9 | Define criteria for project success (I.e. critical success factors) | PMO - EAI | 16 hrs | Tue 5/6/03 | Fri 5/9/03 | 100% |
9 | Define criteria for project success (I.e. critical success factors) | Subject Matter Expert - EAI | 8 hrs | Tue 5/6/03 | Fri 5/9/03 | 100% |
10 | Identify assumptions and risks | Project Manager - EAI | 8 hrs | Mon 5/12/03 | Thu 5/15/03 | 100% |
10 | Identify assumptions and risks | PMO - EAI | 16 hrs | Mon 5/12/03 | Thu 5/15/03 | 100% |
10 | Identify assumptions and risks | Subject Matter Expert - EAI | 8 hrs | Mon 5/12/03 | Thu 5/15/03 | 100% |
11 | Identify and establish project organization [internal & external] | Project Manager - EAI | 8 hrs | Fri 5/16/03 | Mon 5/19/03 | 100% |
11 | Identify and establish project organization [internal & external] | PMO - EAI | 16 hrs | Fri 5/16/03 | Mon 5/19/03 | 100% |
11 | Identify and establish project organization [internal & external] | Subject Matter Expert - EAI | 8 hrs | Fri 5/16/03 | Mon 5/19/03 | 100% |
12 | Establish and implement change control process | Subject Matter Expert - EAI | 8 hrs | Tue 5/20/03 | Fri 5/23/03 | 100% |
12 | Establish and implement change control process | PMO - EAI | 16 hrs | Tue 5/20/03 | Fri 5/23/03 | 100% |
12 | Establish and implement change control process | Project Manager - EAI | 16 hrs | Tue 5/20/03 | Fri 5/23/03 | 100% |
13 | Document project charter and communicate to stake holders | Project Manager - EAI | 16 hrs | Mon 5/26/03 | Tue 5/27/03 | 100% |
13 | Document project charter and communicate to stake holders | PMO - EAI | 8 hrs | Mon 5/26/03 | Tue 5/27/03 | 100% |
14 | Develop Work Plan and Communicate | Project Manager - EAI | 16 hrs | Wed 5/28/03 | Mon 6/2/03 | 100% |
14 | Develop Work Plan and Communicate | PMO - EAI | 8 hrs | Wed 5/28/03 | Mon 6/2/03 | 100% |
18 | Define Business Requirements | Project Manager - EAI | 40 hrs | Thu 6/26/03 | Mon 6/30/03 | 100% |
18 | Define Business Requirements | Quality Assurance/Testing - EAI | 40 hrs | Thu 6/26/03 | Mon 6/30/03 | 100% |
18 | Define Business Requirements | Subject Matter Expert - EAI | 40 hrs | Thu 6/26/03 | Mon 6/30/03 | 100% |
19 | Define Operations Concept | System Architect - EAI | 40 hrs | Tue 7/1/03 | Thu 7/3/03 | 100% |
19 | Define Operations Concept | Subject Matter Expert - EAI | 40 hrs | Tue 7/1/03 | Thu 7/3/03 | 100% |
19 | Define Operations Concept | Quality Assurance/Testing - EAI | 40 hrs | Tue 7/1/03 | Thu 7/3/03 | 100% |
20 | Perform Stakeholder Analysis | Project Manager - EAI | 7.93 hrs | Fri 7/4/03 | Tue 7/8/03 | 100% |
20 | Perform Stakeholder Analysis | Quality Assurance/Testing - EAI | 48.08 hrs | Fri 7/4/03 | Tue 7/8/03 | 100% |
20 | Perform Stakeholder Analysis | Subject Matter Expert - EAI | 48.08 hrs | Fri 7/4/03 | Tue 7/8/03 | 100% |
20 | Perform Stakeholder Analysis | System Architect - EAI | 39.9 hrs | Fri 7/4/03 | Tue 7/8/03 | 100% |
21 | Construct/Deliver Communication Materials | PMO - EAI | 48 hrs | Wed 7/9/03 | Fri 7/11/03 | 100% |
21 | Construct/Deliver Communication Materials | Subject Matter Expert - EAI | 48 hrs | Wed 7/9/03 | Fri 7/11/03 | 100% |
21 | Construct/Deliver Communication Materials | System Architect - EAI | 48 hrs | Wed 7/9/03 | Fri 7/11/03 | 100% |
22 | Conduct Startup Technical Review | Subject Matter Expert - EAI | 48 hrs | Mon 7/14/03 | Wed 7/16/03 | 100% |
24 | Document Assumption and Risk Mitigations | PMO - EAI | 40 hrs | Thu 6/26/03 | Thu 6/26/03 | 100% |
25 | Identify Framework Setup Team | Project Manager - EAI | 16 hrs | Fri 6/27/03 | Fri 6/27/03 | 100% |
25 | Identify Framework Setup Team | PMO - EAI | 8 hrs | Fri 6/27/03 | Fri 6/27/03 | 100% |
25 | Identify Framework Setup Team | Subject Matter Expert - EAI | 8 hrs | Fri 6/27/03 | Fri 6/27/03 | 100% |
26 | Plan Project SQA activities | Project Manager - EAI | 40 hrs | Mon 6/30/03 | Mon 6/30/03 | 100% |
26 | Plan Project SQA activities | PMO - EAI | 16 hrs | Mon 6/30/03 | Mon 6/30/03 | 100% |
26 | Plan Project SQA activities | Quality Assurance/Testing - EAI | 40 hrs | Mon 6/30/03 | Mon 6/30/03 | 100% |
26 | Plan Project SQA activities | Subject Matter Expert - EAI | 16 hrs | Mon 6/30/03 | Mon 6/30/03 | 100% |
27 | Update Work plan and communicate | Project Manager - EAI | 16 hrs | Tue 7/1/03 | Tue 7/1/03 | 100% |
27 | Update Work plan and communicate | PMO - EAI | 8 hrs | Tue 7/1/03 | Tue 7/1/03 | 100% |
31 | Define System Requirements | Quality Assurance/Testing - EAI | 16 hrs | Thu 7/17/03 | Fri 7/18/03 | 100% |
31 | Define System Requirements | Subject Matter Expert - EAI | 40 hrs | Thu 7/17/03 | Fri 7/18/03 | 100% |
31 | Define System Requirements | System Architect - EAI | 24 hrs | Thu 7/17/03 | Fri 7/18/03 | 100% |
32 | Analyze And Allocate System Requirements | System Architect - EAI | 40 hrs | Mon 7/21/03 | Mon 7/21/03 | 100% |
33 | Revisit & Update Infrastructure Conceptual Design | Subject Matter Expert - EAI | 40 hrs | Tue 7/22/03 | Wed 7/23/03 | 100% |
34 | Evaluate Recommended Solutions | Quality Assurance/Testing - EAI | 16 hrs | Thu 7/24/03 | Fri 7/25/03 | 100% |
34 | Evaluate Recommended Solutions | Subject Matter Expert - EAI | 32 hrs | Thu 7/24/03 | Fri 7/25/03 | 100% |
34 | Evaluate Recommended Solutions | System Architect - EAI | 32 hrs | Thu 7/24/03 | Fri 7/25/03 | 100% |
35 | Define User Acceptance Criteria | PMO - EAI | 24 hrs | Mon 7/28/03 | Mon 7/28/03 | 100% |
35 | Define User Acceptance Criteria | Subject Matter Expert - EAI | 40 hrs | Mon 7/28/03 | Mon 7/28/03 | 100% |
35 | Define User Acceptance Criteria | System Architect - EAI | 16 hrs | Mon 7/28/03 | Mon 7/28/03 | 100% |
36 | Perform Requirements Technical Reviews | PMO - EAI | 8 hrs | Tue 7/29/03 | Wed 7/30/03 | 100% |
37 | Construct/Deliver Communication Materials | Subject Matter Expert - EAI | 40 hrs | Thu 7/31/03 | Fri 8/1/03 | 100% |
39 | Document Assumption and Risk Mitigations | PMO - EAI | 16 hrs | Thu 7/17/03 | Thu 7/17/03 | 100% |
39 | Document Assumption and Risk Mitigations | Project Manager - EAI | 16 hrs | Thu 7/17/03 | Thu 7/17/03 | 100% |
39 | Document Assumption and Risk Mitigations | System Architect - EAI | 24 hrs | Thu 7/17/03 | Thu 7/17/03 | 100% |
40 | Review change control process | Project Manager - EAI | 16 hrs | Fri 7/18/03 | Fri 7/18/03 | 100% |
40 | Review change control process | PMO - EAI | 24 hrs | Fri 7/18/03 | Fri 7/18/03 | 100% |
40 | Review change control process | System Architect - EAI | 16 hrs | Fri 7/18/03 | Fri 7/18/03 | 100% |
41 | Identify critical tasks / activities | Project Manager - EAI | 40 hrs | Mon 7/21/03 | Mon 7/21/03 | 100% |
41 | Identify critical tasks / activities | PMO - EAI | 16 hrs | Mon 7/21/03 | Mon 7/21/03 | 100% |
42 | Update Work plan and communicate | Project Manager - EAI | 24 hrs | Tue 7/22/03 | Wed 7/23/03 | 100% |
42 | Update Work plan and communicate | PMO - EAI | 8 hrs | Tue 7/22/03 | Wed 7/23/03 | 100% |
45 | Finalize User Acceptance Criteria | Project Manager - EAI | 40 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
45 | Finalize User Acceptance Criteria | Quality Assurance/Testing - EAI | 8 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
45 | Finalize User Acceptance Criteria | Subject Matter Expert - EAI | 16 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
45 | Finalize User Acceptance Criteria | System Architect - EAI | 32 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
46 | Develop Component Interface Chart | Infrastructure Support - EAI | 40 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
46 | Develop Component Interface Chart | Quality Assurance/Testing - EAI | 8 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
46 | Develop Component Interface Chart | Subject Matter Expert - EAI | 16 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
46 | Develop Component Interface Chart | System Architect - EAI | 32 hrs | Mon 8/4/03 | Fri 8/8/03 | 100% |
48 | Define S/w Configurations | Infrastructure Support - EAI | 16 hrs | Mon 8/11/03 | Thu 8/14/03 | 100% |
48 | Define S/w Configurations | Quality Assurance/Testing - EAI | 8 hrs | Mon 8/11/03 | Thu 8/14/03 | 100% |
48 | Define S/w Configurations | Subject Matter Expert - EAI | 16 hrs | Mon 8/11/03 | Thu 8/14/03 | 100% |
48 | Define S/w Configurations | System Architect - EAI | 16 hrs | Mon 8/11/03 | Thu 8/14/03 | 100% |
49 | Assess System Impact | Project Manager - EAI | 40 hrs | Mon 8/4/03 | Thu 8/7/03 | 100% |
49 | Assess System Impact | Quality Assurance/Testing - EAI | 8 hrs | Mon 8/4/03 | Thu 8/7/03 | 100% |
49 | Assess System Impact | Subject Matter Expert - EAI | 16 hrs | Mon 8/4/03 | Thu 8/7/03 | 100% |
49 | Assess System Impact | System Architect - EAI | 32 hrs | Mon 8/4/03 | Thu 8/7/03 | 100% |
51 | Perform Functional Requirement Assessment | Project Manager - EAI | 24.17 hrs | Fri 8/15/03 | Tue 8/19/03 | 100% |
51 | Perform Functional Requirement Assessment | Infrastructure Support - EAI | 39.97 hrs | Fri 8/15/03 | Tue 8/19/03 | 100% |
51 | Perform Functional Requirement Assessment | Quality Assurance/Testing - EAI | 7.95 hrs | Fri 8/15/03 | Tue 8/19/03 | 100% |
51 | Perform Functional Requirement Assessment | Subject Matter Expert - EAI | 15.88 hrs | Fri 8/15/03 | Tue 8/19/03 | 100% |
51 | Perform Functional Requirement Assessment | System Architect - EAI | 32.02 hrs | Fri 8/15/03 | Tue 8/19/03 | 100% |
52 | Perform Non-Functional Requirement Assessment | PMO - EAI | 15.93 hrs | Wed 8/20/03 | Fri 8/22/03 | 100% |
52 | Perform Non-Functional Requirement Assessment | Infrastructure Support - EAI | 40.07 hrs | Wed 8/20/03 | Fri 8/22/03 | 100% |
52 | Perform Non-Functional Requirement Assessment | Quality Assurance/Testing - EAI | 7.97 hrs | Wed 8/20/03 | Fri 8/22/03 | 100% |
52 | Perform Non-Functional Requirement Assessment | Subject Matter Expert - EAI | 15.93 hrs | Wed 8/20/03 | Fri 8/22/03 | 100% |
52 | Perform Non-Functional Requirement Assessment | System Architect - EAI | 32.1 hrs | Wed 8/20/03 | Fri 8/22/03 | 100% |
54 | Negotiate Requirements Changes | Project Manager - EAI | 7.75 hrs | Mon 8/25/03 | Mon 9/1/03 | 100% |
54 | Negotiate Requirements Changes | PMO - EAI | 32 hrs | Mon 8/25/03 | Mon 9/1/03 | 100% |
54 | Negotiate Requirements Changes | System Architect - EAI | 40.25 hrs | Mon 8/25/03 | Mon 9/1/03 | 100% |
57 | Document Assumption and Risk Mitigations | Project Manager - EAI | 40 hrs | Mon 8/4/03 | Mon 8/4/03 | 100% |
57 | Document Assumption and Risk Mitigations | PMO - EAI | 16 hrs | Mon 8/4/03 | Mon 8/4/03 | 100% |
58 | Identify critical tasks / activities | Project Manager - EAI | 40 hrs | Tue 8/5/03 | Tue 8/5/03 | 100% |
58 | Identify critical tasks / activities | PMO - EAI | 16 hrs | Tue 8/5/03 | Tue 8/5/03 | 100% |
59 | Update Work plan and communicate | Project Manager - EAI | 24 hrs | Wed 8/6/03 | Wed 8/6/03 | 100% |
59 | Update Work plan and communicate | PMO - EAI | 8 hrs | Wed 8/6/03 | Wed 8/6/03 | 100% |
66 | S/W Components, Integration And System | Database Administrator - EAI | 24.03 hrs | Tue 9/2/03 | Thu 9/4/03 | 100% |
66 | S/W Components, Integration And System | Infrastructure Support - EAI | 39.9 hrs | Tue 9/2/03 | Thu 9/4/03 | 100% |
66 | S/W Components, Integration And System | Subject Matter Expert - EAI | 80.05 hrs | Tue 9/2/03 | Thu 9/4/03 | 100% |
67 | Operational Dry Run | Database Administrator - EAI | 15.93 hrs | Fri 9/5/03 | Tue 9/9/03 | 100% |
67 | Operational Dry Run | Infrastructure Support - EAI | 15.93 hrs | Fri 9/5/03 | Tue 9/9/03 | 100% |
67 | Operational Dry Run | Subject Matter Expert - EAI | 32.12 hrs | Fri 9/5/03 | Tue 9/9/03 | 100% |
68 | Develop Business Continuity Plan | PMO - EAI | 16 hrs | Wed 9/10/03 | Fri 9/12/03 | 100% |
68 | Develop Business Continuity Plan | Subject Matter Expert - EAI | 8 hrs | Wed 9/10/03 | Fri 9/12/03 | 100% |
69 | Develop implementation plan | PMO - EAI | 16 hrs | Mon 9/15/03 | Wed 9/17/03 | 100% |
69 | Develop implementation plan | Subject Matter Expert - EAI | 8 hrs | Mon 9/15/03 | Wed 9/17/03 | 100% |
71 | Evaluate Existing component Re-Use | Subject Matter Expert - EAI | 80 hrs | Thu 9/18/03 | Mon 9/22/03 | 100% |
72 | Perform Detailed Design Technical Review | Project Manager - EAI | 40 hrs | Tue 9/23/03 | Thu 9/25/03 | 100% |
73 | Construct / Deliver Communication Materials | PMO - EAI | 16 hrs | Fri 9/26/03 | Tue 9/30/03 | 100% |
74 | Monitor Developer Communications | Project Manager - EAI | 32 hrs | Tue 9/2/03 | Wed 9/3/03 | 100% |
74 | Monitor Developer Communications | PMO - EAI | 8 hrs | Tue 9/2/03 | Wed 9/3/03 | 100% |
76 | Document Assumption and Risk Mitigations | Project Manager - EAI | 40 hrs | Tue 9/2/03 | Mon 9/8/03 | 100% |
76 | Document Assumption and Risk Mitigations | PMO - EAI | 16 hrs | Tue 9/2/03 | Mon 9/8/03 | 100% |
77 | Review change control process | Project Manager - EAI | 40 hrs | Tue 9/9/03 | Mon 9/15/03 | 100% |
77 | Review change control process | PMO - EAI | 16 hrs | Tue 9/9/03 | Mon 9/15/03 | 100% |
78 | Identify critical tasks / activities | Project Manager - EAI | 40 hrs | Tue 9/16/03 | Mon 9/22/03 | 100% |
78 | Identify critical tasks / activities | PMO - EAI | 16 hrs | Tue 9/16/03 | Mon 9/22/03 | 100% |
79 | Update Work plan and communicate | Project Manager - EAI | 24.07 hrs | Tue 9/23/03 | Thu 9/25/03 | 100% |
79 | Update Work plan and communicate | PMO - EAI | 7.93 hrs | Tue 9/23/03 | Thu 9/25/03 | 100% |
82 | Install complementary software (e.g JDK, Network tools etc) | Database Administrator - EAI | 10.57 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
82 | Install complementary software (e.g JDK, Network tools etc) | Infrastructure Support - EAI | 67.62 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
82 | Install complementary software (e.g JDK, Network tools etc) | Subject Matter Expert - EAI | 33.82 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
83 | Build / Customize Components | Infrastructure Support - EAI | 80 hrs | Wed 10/8/03 | Tue 10/14/03 | 100% |
83 | Build / Customize Components | Subject Matter Expert - EAI | 40 hrs | Wed 10/8/03 | Tue 10/14/03 | 100% |
84 | Integrate System Components | Infrastructure Support - EAI | 80 hrs | Wed 10/15/03 | Tue 10/21/03 | 100% |
84 | Integrate System Components | Subject Matter Expert - EAI | 40 hrs | Wed 10/15/03 | Tue 10/21/03 | 100% |
85 | Perform Unit Testing | Infrastructure Support - EAI | 80 hrs | Wed 10/22/03 | Tue 10/28/03 | 100% |
86 | Update Business Continuity Plan | PMO - EAI | 8 hrs | Wed 10/1/03 | Wed 10/1/03 | 100% |
86 | Update Business Continuity Plan | Subject Matter Expert - EAI | 8 hrs | Wed 10/1/03 | Wed 10/1/03 | 100% |
87 | Update implementation plan | Subject Matter Expert - EAI | 8 hrs | Wed 10/1/03 | Thu 10/2/03 | 100% |
87 | Update implementation plan | PMO - EAI | 8 hrs | Wed 10/1/03 | Thu 10/2/03 | 100% |
88 | Finalize System Test Plans And Specifications | Subject Matter Expert - EAI | 24 hrs | Wed 10/1/03 | Fri 10/3/03 | 100% |
89 | Perform Integration Testing | Infrastructure Support - EAI | 40 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
91 | System Operational Procedures | Subject Matter Expert - EAI | 40 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
92 | User Manual | Subject Matter Expert - EAI | 80 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
93 | Perform System Test Readiness Technical Review | Project Manager - EAI | 40 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
94 | Construct / Deliver Communication Materials | PMO - EAI | 16 hrs | Wed 10/1/03 | Thu 10/2/03 | 100% |
95 | Monitor Vendor Communications | Project Manager - EAI | 40 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
97 | Document Assumption and Risk Mitigations | Project Manager - EAI | 44.8 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
97 | Document Assumption and Risk Mitigations | PMO - EAI | 11.2 hrs | Wed 10/1/03 | Tue 10/7/03 | 100% |
98 | Review change control process | Project Manager - EAI | 44.8 hrs | Wed 10/8/03 | Tue 10/14/03 | 100% |
98 | Review change control process | PMO - EAI | 11.2 hrs | Wed 10/8/03 | Tue 10/14/03 | 100% |
99 | Identify critical tasks / activities | Project Manager - EAI | 44.8 hrs | Wed 10/15/03 | Tue 10/21/03 | 100% |
99 | Identify critical tasks / activities | PMO - EAI | 11.2 hrs | Wed 10/15/03 | Tue 10/21/03 | 100% |
100 | Update Work plan and communicate | Project Manager - EAI | 24.62 hrs | Wed 10/22/03 | Fri 10/24/03 | 100% |
100 | Update Work plan and communicate | PMO - EAI | 7.38 hrs | Wed 10/22/03 | Fri 10/24/03 | 100% |
103 | Train Operational Dry Run (ODR) Participants | Infrastructure Support - EAI | 16 hrs | Wed 10/29/03 | Thu 10/30/03 | 100% |
103 | Train Operational Dry Run (ODR) Participants | Quality Assurance/Testing - EAI | 16 hrs | Wed 10/29/03 | Thu 10/30/03 | 100% |
105 | Stress Testing | Infrastructure Support - EAI | 80 hrs | Fri 10/31/03 | Thu 11/6/03 | 100% |
105 | Stress Testing | Subject Matter Expert - EAI | 80 hrs | Fri 10/31/03 | Thu 11/6/03 | 100% |
106 | Operational Dry Run (Business Processes) | System Architect - EAI | 80 hrs | Fri 11/7/03 | Thu 11/13/03 | 100% |
106 | Operational Dry Run (Business Processes) | Infrastructure Support - EAI | 80 hrs | Fri 11/7/03 | Thu 11/13/03 | 100% |
107 | Perform User Acceptance Test | Infrastructure Support - EAI | 40 hrs | Fri 11/14/03 | Thu 11/20/03 | 100% |
107 | Perform User Acceptance Test | Subject Matter Expert - EAI | 40 hrs | Fri 11/14/03 | Thu 11/20/03 | 100% |
108 | Conduct Business Continuity Test | Subject Matter Expert - EAI | 16 hrs | Fri 11/21/03 | Fri 11/21/03 | 100% |
109 | Update System Documentation | PMO - EAI | 8 hrs | Wed 10/29/03 | Wed 10/29/03 | 100% |
110 | Conduct IT Certification | PMO - EAI | 8 hrs | Mon 11/24/03 | Mon 11/24/03 | 100% |
111 | Perform Pre-Implementation Technical Review | Subject Matter Expert - EAI | 8 hrs | Tue 11/25/03 | Tue 11/25/03 | 100% |
112 | Finalize Business Continuity Plan | PMO - EAI | 4 hrs | Mon 11/24/03 | Mon 11/24/03 | 100% |
112 | Finalize Business Continuity Plan | Subject Matter Expert - EAI | 4 hrs | Mon 11/24/03 | Mon 11/24/03 | 100% |
113 | Finalize Implementation plan | PMO - EAI | 8 hrs | Wed 10/29/03 | Thu 10/30/03 | 100% |
113 | Finalize Implementation plan | Subject Matter Expert - EAI | 8 hrs | Wed 10/29/03 | Thu 10/30/03 | 100% |
114 | Construct / Deliver Communication Materials | PMO - EAI | 16 hrs | Wed 10/29/03 | Wed 10/29/03 | 100% |
115 | Monitor Vendor Communications | Project Manager - EAI | 24 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
115 | Monitor Vendor Communications | PMO - EAI | 16 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
117 | Document Assumption and Risk Mitigations | Project Manager - EAI | 44.8 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
117 | Document Assumption and Risk Mitigations | PMO - EAI | 11.2 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
118 | Review change control process | PMO - EAI | 11.2 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
118 | Review change control process | Project Manager - EAI | 44.8 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
119 | Identify critical tasks / activities | PMO - EAI | 11.2 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
119 | Identify critical tasks / activities | Project Manager - EAI | 44.8 hrs | Wed 10/29/03 | Tue 11/4/03 | 100% |
120 | Update Work plan and communicate | Project Manager - EAI | 24.07 hrs | Wed 10/29/03 | Fri 10/31/03 | 100% |
120 | Update Work plan and communicate | PMO - EAI | 7.93 hrs | Wed 10/29/03 | Fri 10/31/03 | 100% |
123 | Execute Implementation Plan | Project Manager - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
125 | Development Environment | Business Analyst - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
125 | Development Environment | Database Administrator - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
125 | Development Environment | Infrastructure Support - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
125 | Development Environment | Quality Assurance/Testing - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
125 | Development Environment | Subject Matter Expert - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
125 | Development Environment | System Architect - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
126 | Test Environment | System Architect - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
126 | Test Environment | Subject Matter Expert - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
126 | Test Environment | Quality Assurance/Testing - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
126 | Test Environment | Infrastructure Support - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
126 | Test Environment | Database Administrator - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
126 | Test Environment | Business Analyst - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
127 | Staging Environment | Business Analyst - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
127 | Staging Environment | Database Administrator - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
127 | Staging Environment | Infrastructure Support - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
127 | Staging Environment | Quality Assurance/Testing - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
127 | Staging Environment | Subject Matter Expert - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
127 | Staging Environment | System Architect - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
128 | DR Environment | System Architect - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
128 | DR Environment | Subject Matter Expert - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
128 | DR Environment | Quality Assurance/Testing - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
128 | DR Environment | Infrastructure Support - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
128 | DR Environment | Database Administrator - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
128 | DR Environment | Business Analyst - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
129 | Production Environment | Business Analyst - EAI | 18.58 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
129 | Production Environment | Database Administrator - EAI | 15.48 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
129 | Production Environment | Infrastructure Support - EAI | 15.48 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
129 | Production Environment | Quality Assurance/Testing - EAI | 15.48 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
129 | Production Environment | Subject Matter Expert - EAI | 15.48 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
129 | Production Environment | System Architect - EAI | 15.48 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
130 | Train Operational Staff | Infrastructure Support - EAI | 80 hrs | Fri 11/28/03 | Fri 12/5/03 | 100% |
131 | Test Operational Procedures | Infrastructure Support - EAI | 40 hrs | Mon 12/8/03 | Fri 12/12/03 | 100% |
132 | Finalize System Documentation | PMO - EAI | 16 hrs | Mon 12/15/03 | Tue 12/16/03 | 100% |
132 | Finalize System Documentation | Infrastructure Support - EAI | 8 hrs | Mon 12/15/03 | Tue 12/16/03 | 100% |
133 | Construct / Deliver Communication Materials | PMO - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
134 | Monitor Developer Communications | PMO - EAI | 8 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
134 | Monitor Developer Communications | Project Manager - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
136 | Document Assumption and Risk Mitigations | Project Manager - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
136 | Document Assumption and Risk Mitigations | PMO - EAI | 24 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
136 | Document Assumption and Risk Mitigations | Infrastructure Support - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
137 | Review change control process | Project Manager - EAI | 16 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
137 | Review change control process | PMO - EAI | 40 hrs | Wed 11/26/03 | Thu 11/27/03 | 100% |
138 | Identify critical tasks / activities | Project Manager - EAI | 25 hrs | Wed 11/26/03 | Fri 11/28/03 | 100% |
138 | Identify critical tasks / activities | PMO - EAI | 15.5 hrs | Wed 11/26/03 | Fri 11/28/03 | 100% |
138 | Identify critical tasks / activities | System Architect - EAI | 15.5 hrs | Wed 11/26/03 | Fri 11/28/03 | 100% |
139 | Update Work plan and communicate | Project Manager - EAI | 32 hrs | Wed 11/26/03 | Mon 12/1/03 | 100% |
142 | Identify Support Team | Project Manager - EAI | 8 hrs | Mon 11/24/03 | Tue 11/25/03 | 100% |
142 | Identify Support Team | PMO - EAI | 8 hrs | Mon 11/24/03 | Tue 11/25/03 | 100% |
143 | Define Application Handover Plan | Project Manager - EAI | 7.93 hrs | Mon 11/24/03 | Wed 11/26/03 | 100% |
143 | Define Application Handover Plan | PMO - EAI | 7.93 hrs | Mon 11/24/03 | Wed 11/26/03 | 100% |
143 | Define Application Handover Plan | Business Analyst - EAI | 16.12 hrs | Mon 11/24/03 | Wed 11/26/03 | 100% |
143 | Define Application Handover Plan | Database Administrator - EAI | 7.93 hrs | Mon 11/24/03 | Wed 11/26/03 | 100% |
143 | Define Application Handover Plan | Subject Matter Expert - EAI | 16.12 hrs | Mon 11/24/03 | Wed 11/26/03 | 100% |
143 | Define Application Handover Plan | System Architect - EAI | 7.93 hrs | Mon 11/24/03 | Wed 11/26/03 | 100% |
144 | Create a primary Support Plan | Project Manager - EAI | 8 hrs | Thu 11/27/03 | Tue 12/2/03 | 100% |
144 | Create a primary Support Plan | PMO - EAI | 8 hrs | Thu 11/27/03 | Tue 12/2/03 | 100% |
144 | Create a primary Support Plan | Business Analyst - EAI | 16 hrs | Thu 11/27/03 | Tue 12/2/03 | 100% |
144 | Create a primary Support Plan | Database Administrator - EAI | 8 hrs | Thu 11/27/03 | Tue 12/2/03 | 100% |
144 | Create a primary Support Plan | Subject Matter Expert - EAI | 16 hrs | Thu 11/27/03 | Tue 12/2/03 | 100% |
144 | Create a primary Support Plan | System Architect - EAI | 8 hrs | Thu 11/27/03 | Tue 12/2/03 | 100% |
145 | Refine the support process | Business Analyst - EAI | 8 hrs | Wed 12/3/03 | Mon 12/8/03 | 100% |
145 | Refine the support process | Subject Matter Expert - EAI | 8 hrs | Wed 12/3/03 | Mon 12/8/03 | 100% |
145 | Refine the support process | System Architect - EAI | 8 hrs | Wed 12/3/03 | Mon 12/8/03 | 100% |
146 | Details of all servers | Business Analyst - EAI | 8 hrs | Wed 12/3/03 | Mon 12/8/03 | 100% |
146 | Details of all servers | Subject Matter Expert - EAI | 16 hrs | Wed 12/3/03 | Mon 12/8/03 | 100% |
146 | Details of all servers | System Architect - EAI | 16 hrs | Wed 12/3/03 | Mon 12/8/03 | 100% |
147 | Define System Operation Procedure | Application Developer - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
147 | Define System Operation Procedure | Business Analyst - EAI | 16 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
147 | Define System Operation Procedure | Database Administrator - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
147 | Define System Operation Procedure | Quality Assurance/Testing - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
147 | Define System Operation Procedure | Subject Matter Expert - EAI | 16 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
147 | Define System Operation Procedure | System Architect - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
148 | Define Build Procedure | Application Developer - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
148 | Define Build Procedure | Business Analyst - EAI | 16 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
148 | Define Build Procedure | Database Administrator - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
148 | Define Build Procedure | Quality Assurance/Testing - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
148 | Define Build Procedure | Subject Matter Expert - EAI | 16 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
148 | Define Build Procedure | System Architect - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
149 | Define QA Procedure | Application Developer - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
149 | Define QA Procedure | Business Analyst - EAI | 16 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
149 | Define QA Procedure | Database Administrator - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
149 | Define QA Procedure | Quality Assurance/Testing - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
149 | Define QA Procedure | Subject Matter Expert - EAI | 16 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
149 | Define QA Procedure | System Architect - EAI | 8 hrs | Tue 12/9/03 | Fri 12/12/03 | 100% |
150 | Define Release Procedure | Application Developer - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
150 | Define Release Procedure | Business Analyst - EAI | 16 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
150 | Define Release Procedure | Database Administrator - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
150 | Define Release Procedure | Quality Assurance/Testing - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
150 | Define Release Procedure | Subject Matter Expert - EAI | 16 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
150 | Define Release Procedure | System Architect - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
151 | Define Defect Life Cycle Procedure | Application Developer - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
151 | Define Defect Life Cycle Procedure | Business Analyst - EAI | 16 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
151 | Define Defect Life Cycle Procedure | Quality Assurance/Testing - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
151 | Define Defect Life Cycle Procedure | Subject Matter Expert - EAI | 16 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
151 | Define Defect Life Cycle Procedure | System Architect - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
152 | Define Support level Process | Business Analyst - EAI | 16 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
152 | Define Support level Process | Quality Assurance/Testing - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
152 | Define Support level Process | Subject Matter Expert - EAI | 16 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
152 | Define Support level Process | System Architect - EAI | 8 hrs | Mon 12/15/03 | Thu 12/18/03 | 100% |
153 | Complete handover to support team | Application Developer - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | Business Analyst - EAI | 16 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | Database Administrator - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | Quality Assurance/Testing - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | Subject Matter Expert - EAI | 16 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | System Architect - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | Project Manager - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
153 | Complete handover to support team | PMO - EAI | 16 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
154 | Train support team on technology | Application Developer - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
154 | Train support team on technology | Business Analyst - EAI | 16 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
154 | Train support team on technology | Database Administrator - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
154 | Train support team on technology | Quality Assurance/Testing - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
154 | Train support team on technology | Subject Matter Expert - EAI | 16 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
154 | Train support team on technology | System Architect - EAI | 8 hrs | Fri 12/19/03 | Wed 12/24/03 | 100% |
156 | Establish and implement change control process | Project Manager - EAI | 16 hrs | Mon 11/24/03 | Thu 11/27/03 | 100% |
156 | Establish and implement change control process | PMO - EAI | 16 hrs | Mon 11/24/03 | Thu 11/27/03 | 100% |
156 | Establish and implement change control process | Business Analyst - EAI | 24 hrs | Mon 11/24/03 | Thu 11/27/03 | 100% |
156 | Establish and implement change control process | Quality Assurance/Testing - EAI | 16 hrs | Mon 11/24/03 | Thu 11/27/03 | 100% |
156 | Establish and implement change control process | Subject Matter Expert - EAI | 24 hrs | Mon 11/24/03 | Thu 11/27/03 | 100% |
156 | Establish and implement change control process | System Architect - EAI | 16 hrs | Mon 11/24/03 | Thu 11/27/03 | 100% |
157 | Document project charter and communicate to stakeholders | Project Manager - EAI | 8 hrs | Fri 11/28/03 | Wed 12/3/03 | 100% |
157 | Document project charter and communicate to stakeholders | PMO - EAI | 8 hrs | Fri 11/28/03 | Wed 12/3/03 | 100% |